blue News Logo
  • Start
  • Sport
  • Switzerland
  • International
  • Football
  • People
  • MyTech
  • Lifestyle
blue News Logo
  • Start
  • Sport
  • Switzerland
  • International
  • Football
  • People
  • MyTech
  • Lifestyle
blue NewsSwitzerlandInternationalSportFootballDigitalPeopleLifestyle
About blueOur CompanyWork at blueJobs
blue+blue TVblue Sportblue SuperMax
blue CinemaMoviesComing soonDealsMemberclubs
Residential CustomersMobileInternetTVCombi SubscriptionDevicesSupport & ServiceHelp
ToolsEmailCustomer SupportPhone BookShop Finder
blue News
SwitzerlandInternationalSportFootballDigitalPeopleLifestyle
About blue
Our CompanyWork at blueJobs
blue+
blue TVblue Sportblue SuperMax
blue Cinema
MoviesComing soonDealsMemberclubs
Residential Customers
MobileInternetTVCombi SubscriptionDevicesSupport & ServiceHelp
Tools
EmailCustomer SupportPhone BookShop Finder
AdvertisingLegalPrivacy PolicyImprintJournalistic Guidelinesblue News AppFAQ
DEFRITEN
DEFRITEN
1000 kilometers of cable laid incorrectly - Stuttgart 21 is threatened by the next mega-breakdown
HomeChevron rightNewsChevron rightInternational

Found an error?

Report now

Opening not before 2031

1000 kilometers of cable laid incorrectly - Stuttgart 21 threatens the next mega-breakdown

According to media reports, the opening of Stuttgart 21 could be further delayed. (archive picture)

According to media reports, the opening of Stuttgart 21 could be further delayed. (archive picture)

Christoph Schmidt/dpa

Stuttgart 21 is not due to be completed until 2031. This is apparently also due to the fact that around 1000 kilometers of cable were laid incorrectly.

DPA

DPA

10.06.2026, 13:43•10.06.2026, 15:24

No time? böue News summarizes for you

  • According to SWR, more than 1000 kilometers of cable and cable shafts are said to have been laid incorrectly at Stuttgart 21.
  • Full commissioning of the project could therefore be delayed until the end of 2031.
  • The costs of the controversial large-scale project have now risen from around 3 billion to over 11 billion euros.

The major German railroad project Stuttgart 21 could be completed later than recently assumed. As was announced at the beginning of the week, those involved now expect the project to not be fully operational until the end of 2031.

A report by SWR is particularly explosive: according to the report, more than 1000 kilometers of cables and cable shafts are said to have been laid incorrectly. A large proportion of these would have to be replaced. Deutsche Bahn did not want to comment on the information and referred to a meeting of the steering committee at the end of June.

Deutsche Bahn remains silent ahead of important decision

Deutsche Bahn announced that it would provide information about a new commissioning concept on June 26. The company is currently not commenting on speculation about further delays.

Nevertheless, according to several media reports, travelers should benefit from the first improvements as early as the end of 2027. For example, some of the long distances to the platforms required today could be shortened.

Last November, Deutsche Bahn had already canceled a partial opening planned for the end of 2026. Railroad boss Evelyn Palla justified this at the time with difficulties in the digitalization of the railroad junction.

Stuttgart is to be the first major rail hub in Germany to be operated completely digitally. Long-distance trains, regional trains and suburban trains are to run exclusively with the European Train Control System (ETCS). Traditional light signals are no longer planned. However, the technical implementation is proving to be much more complicated than expected.

From billion-euro project to permanent construction site symbol

Stuttgart 21 has been under construction since 2010. When the federal government, Deutsche Bahn and project partners agreed on the financing in 2009, they still expected the project to open in 2019.

At that time, the costs were estimated at around 4.5 billion euros. In early plans, there was even talk of only around 3 billion euros. Deutsche Bahn is now calculating costs of around 11.3 billion euros.

Stuttgart 21 not only includes the new underground main station. The project also includes new stations, tunnels, bridges and track systems as well as the high-speed line between Wendlingen and Ulm, which will open in 2022.

More About this Topic

First details have leaked
First details have leaked

Trump Announces a "Huge Revelation" — Now It's Clear What It's About

4
with Video
After more than a century
After more than a century

Europe's Most Annoying Border Is Finally Gone

British Overseas Territory
British Overseas Territory

"End of the Ordeal": Spain-Gibraltar Border Now Unrestricted

A Promise Kept
A Promise Kept

Daughter Fulfills Her Mother's Last Wish—and Brings Back 40 Kilo of Sand

Most Read

1Siemens Energy will be renamed "Omterra"
2Swiss Man Insults a Holiday—Now He Faces 15 Months in Prison in Bali
333-Year-Old Polish Woman Dies in a Fall on Dufourspitze in Valais
4These rules for tourists are intended to prevent conflicts with locals
5A gorgeous head of hair for mom and a flight to remember