Bad weather Still no timetable for temporary bridge over the Maggia

SDA

10.7.2024 - 16:00

A temporary bridge is to temporarily replace the Visletto bridge, which was destroyed by a storm. (archive picture)
A temporary bridge is to temporarily replace the Visletto bridge, which was destroyed by a storm. (archive picture)
Keystone

A temporary bridge is to be built by the Swiss army over the next few weeks to the north of the Visletto Bridge, which collapsed as a result of the storms. The Ticino emergency staff were still unable to present an exact timetable on Wednesday.

On the one hand, the construction of such a bridge normally takes several months, Diego Rodoni, head of the civil engineering department, told the media in Locarno on Wednesday.

On the other hand, it is not yet clear what kind of subsoil will be found below the surface. Due to the high water level of the Maggia, these investigations could not have been carried out so quickly.

The temporary bridge was designed for a service life of around one year, continued Rodoni. It would be a "matter of weeks" before the bridge was in place.